Margins & Allowances
Estimation
Weight & VCG
Margins
Typically in ship design, a certain amount of margins are included into
the light ship weight and VCG estimates to account for;
- uncertainties in
the calculations and weights used to estimate the vessel's lightship
weight,
- potential design
changes that will occur during construction,
- weight growth
during detailed design and construction that can occur as more detailed
design is performed and better estimates & calculations are
undertaken,
- potential
revisions to the contract during design and construction, and
- possible
additional equipment etc that the government may want to add to the
vessel during design and construction, etc.
Looking
at the trend lines I have developed for estimating the Group 100
to 700 weights and the trend lines for the VCG
estimates for these groups you can see a fair amount of spread in
the data points. Additionally, for many of the ships used to
develop those curves, I actually found multiple, sometimes slightly
conflicting estimates for the different weight groups. As such there
would be a lot of uncertainty in any weight estimates developed from
these curves. So, it makes good sense to also include some
margins into the lightship weight estimates developed using the
evaluation tool described on this website, although it's not all that
clear how much margin would be appropriate.
Not too long ago the US Navy put together a
document providing guidelines for how much margin would be appropriate
for early stage designs based on how risky the design is and how much
effort the ship builder is willing to put into mitigating weight growth
during construction. This document is called NAVSEAINST 9096.6B
"Policy for Weight and Vertical Center of Gravity Above Bottom of Keel
(KG) Margin for Surface Ships". As I understand it, much of this
information is also reproduced in "Recommended Practice Number 14" from
the Society of Allied Weight Engineers, entitled "Weight Estimating and
Margin Manual for Marine Vehicles".
In these documents the USN categorizes ship designs into five different
categories by how much risk is inherent in the design. These
categories include:
- Developmental designs
with a high level of uncertainty
- New concept design with
some significant level of uncertainty
- Designs similar to
existing designs but with major changes and an associated level of some
uncertainty
- Designs similar to
existing designs with minor changes and only a small level of
uncertainty,
- Follow-on designs
with only minor changes and almost no uncertainty
For the purposes of this
design evaluation tool, I'd suggest that;
- if you were
trying to recreate an existing design, I would define it as a Category
5 vessel,
- if you were
trying to investigate a relatively simple modification to an existing
design, such as investigating fitting an alternate existing
weapons, sensor, or propulsion engine, etc or if you were trying to
investigate a design that, while not being directly derived from an
existing design, it is still very conventional, and uses existing
weapons, sensors, and propulsion engines, etc I would also define these
as Category 4 vessels,
- if you were trying to
investigate a more complex modification to an existing design, such as
investigating fitting a limited number of alternate not currently
existing/developmental gun sensor, or propulsion engine, etc or if
you were considering fitting a completely new propulsion plant, or if
you were trying to investigate a design that, while not being directly
derived from an existing design, it is still very conventional, but
uses a limited number of not currently existing/developmental
weapon, sensor, or propulsion engine, etc I would also define these as Category
3 vessels,
- If you were trying to
investigate any other form of conventional displacement monohull that
includes a significant number of not currently
existing/developmental gun sensor, or propulsion engine, etc or
some form of radical/new propulsion plant, then I would define these as
Category 2 vessels, and finally
- If you were
trying to do something else, like a multihull or an all aluminum or
composite hull larger than any previously built vessel etc, for now I'd
guess that would probably best be described as a Category 1 vessel.
Perhaps in the future I might
try and come up with some method to better categorize a design but for
now, for the purposes of this evaluation tool, here are some examples
of the type of designs I would expect to fall into each Category:
- Recreating
vessels like the FFG7, DD963, DDG51, & CG47 etc would all be Category
5 type designs
- Recreating the
FFG7 but substituting a 57mm or 127mm gun for the 76mm gun, or a VLS
for the Mk13 launcher would be a Category 4 type
design. Similarly, investigating a totally new conventional
monohull design, outfitting with an existing gun (like the 127mm Mk45)
and existing sensors (like the SPS-48 and SQS-53 sonar), and existing
gas turbines (like the LM2500) would also probably best be considered a
Category 4 type design.
- Recreating the
DDG51 but substituting a weapon that is still under development or
which was only ever developed as a prototype etc (like the 203mm MCLWG
etc) would probably be a Category 3 design.
Similarly, investigating a modified repeat of the DDG51 with an
alternate power plant based on the MT30 gas turbines would also
probably best be described as a Category 3 design, as
would a completely new (but conventional monohull) with only a limited
amount of developmental equipment (such as if I were to substitute
LM2500+ or MT30 gas turbines into the sample Category 4
vessel noted above)
- Trying to design
a relatively conventional monohull (similar to the DDG51) but outfitted
with SPY3, the AGS gun, PVLS missile launchers, and an integrated
electric drive would probably best be described as a Category 2
type design
- For now, trying
to develop a design like the DDX or the trimaran LCS would likely be Category
1 designs (for the monohull LCS I'd guess that you should
probably consider it part way between a Category 1 and Category
2 design)
The document noted above
provides a curve relating weight margins (as a percentage of lightship
weight) to the extent of weight control that would be needed during
design and construction (and the impacts of the consequences of
exceeding the weight margins) for each of the 5 different design
categories, as shown in the figure below. In general, for the
region defined as;
- HIGH Risk
- There is a high possibility that the design might not meet safety
limits (subdivision, strength, service life allowances), which might
result in the need to redesign all or part of the ship during detailed
design and construction which could significantly impact the overall
cost and building schedule for the vessel. As such, extreme
weight control measures would be required.
- MODERATE
Risk - For vessels falling in this category it is expected that weights
can be controlled during detailed design and construction by use of an
effective weight control program that would involve incentives,
Not-to-Exceed values, and other risk mitigation measures.
- LOW Risk -
Vessels falling into this category are considered relatively safe
designs with very little uncertainty where weight growth can be
controlled during detailed design and construction by applying standard
weight control and reporting procedures.
Designing a vessel with only enough margins
such that it would fall into the HIGH Risk category, is
probably not a good idea unless their is a very good reason too, and it
would probably be very costly as extreme weight control measures would
likely mean;
- the potential
need to use a lot of lighter weight materials and equipment to keep
weights down,
- the need to
conduct alot of additional analyses to see where the use of this
lighter weight materials and equipment would be suitable in place of
more conventional stuff,
- a higher overall
material (and potentially labor) cost for the design as the lighter
weight materials and equipment would likely be more costly than more
conventional stuff, as well as
- the potential
impacts to the design and building schedule if it is found necessary to
redesign a large amount of the ship to implement lighter weight
materials and equipment, etc.
For the purposes of
putting together a design evaluation tool I'd suggest prohibiting the
use of margins that would result in the design falling into the HIGH
Risk category (for now).
With respect to designs that fall into the MODERATE Risk
category, as noted above it is expected that weight growth could be
controlled during detailed design and construction so that providing
enough margins for the vessel to fall within this category, is probably
acceptable, but there is probably some additional costs associated with
it (as it will probably require the use of at least some ligher weight
materials and equipment and/or additional engineering, etc).
If a vessel design has enough margins to fall into the LOW risk
category I'd suspect that there probably shouldn't be any appreciable
additional costs, etc associated with that design.
As such, for the design evaluation tool I would suggest the following:
|
Recommended
Wt Margin
|
|
|
Category
|
Description
|
for Moderate Risk |
for Low Risk |
1
|
Developmental designs with a high level of
uncertainty |
15.5% |
26% |
2
|
New concept design with some significant level
of uncertainty |
10% |
18% |
3
|
Designs similar to existing designs but with major
changes and an associated level of some uncertainty |
6% |
12% |
4
|
Designs similar to existing designs with minor changes
and only a small level of uncertainty |
3% |
8% |
5
|
Follow-on designs with only minor changes and almost
no uncertainty |
1% |
6% |
|
Recommended
VCG Margin
|
|
|
Category
|
Description
|
for Moderate Risk |
for Low Risk |
1
|
Developmental designs with a high level of
uncertainty |
10.3% |
16.7% |
2
|
New concept design with some significant level
of uncertainty |
7.0% |
12.0% |
3
|
Designs similar to existing designs but with major
changes and an associated level of some uncertainty |
4.4% |
9.0% |
4
|
Designs similar to existing designs with minor changes
and only a small level of uncertainty |
2.6% |
6.3% |
5
|
Follow-on designs with only minor changes and almost
no uncertainty |
0.5% |
4.2% |
Service Life Weight Allowance
For naval vessels, an allowance is typically made for weight growth
after the ship enters service. This is refered to as a ship's Service
Life Allowance (or SLA). The SAWE
Recommended
Practice #14 - "Weight Estimating and Margin Manual for Marine
Vehicles" document provides the following recommendations for naval
vessels:
Ship Type: |
Weight
|
VCG
|
Anticipated Service Life
|
|
(%) |
(m) |
(ft) |
(Years) |
Combatants |
10.0 |
0.30 |
1.0 |
20 |
Carriers |
7.5 |
0.76 |
2.5 |
30 |
Amphibious warfare
ship types |
|
|
|
|
a. Large deck |
7.5 |
0.76 |
2.5 |
30 |
b. Other |
5.0 |
0.30 |
1.0 |
20 |
Auxiliary ship types |
5.0 |
0.15 |
0.5 |
20 |
Special ships
and craft |
5.0 |
0.15 |
0.5 |
20 |
Notes:
Weight percentage based on the predicted full load departure
displacement at delivery
VCG Values based on the predicted full load departure
VCG @ delivery
|
This document states that "SLAs shall be
included in all new and modified repeat designs such that, when
delivered, each U. S. Navy surface ship shall be capable of
accommodating the anticipated growth of weight and KG during its
service life without compromise of the hull strength, reserve buoyancy,
and stability characteristics established for the class."
The document also notes that "an increased SLA may be required for
ships with longer projected service lives." As such, for now for
surface combatant designs (like corvettes, frigates, destroyers, and
cruisers) I would suggest using a value of 0.5% of a design's
full load displacement @ departure (ie with full fuel tanks and a
complete loadout of stores) as a suitable Service Life Weight
Allowance. |